Smarr CC (GTC-GI-193) — Project Summary

Queue ID
GTC-GI-193
Capacity
2000 MW
Technology
Gas
Status
active
Location
Monroe, GA
Region
Southeast
Developer
—
IA Status
Facility Study

Smarr CC

GTC-GI-193BetaActiveGasGTCLBNL

2,000 MW generation in Monroe, GA · In queue since August 2024 · Proposed COD March 2028

BA: SOCONERC: SERCRC: SOCO

2,000 MW

Capacity

1

Components

Gas

2y 3m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 7m

Facilities Study50%
Queue EntryAug 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-31

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Mar 31, 2028
From queue filing
Developer in saved assessment
Oglethorpe Power Corporation
Status at research time
Construction
LBNL shows Active / Facility Study, but Oglethorpe has broken ground on the 1,425 MW two-unit combined-cycle plant, with Kiewit's The Industrial Co. as EPC and GE Vernova supplying the technology. LBNL lists 2,000 MW against the 1,425 MW the developer reports.
Financing
Secured
USDA announced a record $3.3B loan for Oglethorpe Power's Monroe County, GA gas generation facility (ConstructConnect, reported about 3 days before the search). The exact close date is not given.

Milestones in this assessment

Permit approvedNov 6, 2025

A community post cites an approval dated 11/6/25 for the 1,425 MW Monroe County plant. The approving body is not named and the source is weak.

facebook.com
Groundbreaking2026

Oglethorpe broke ground on the $3.3B, 1,425 MW gas plant near its existing Smarr Energy Facility. The exact date is not given.

electric.coop
Financing close2026Latest in this assessment

USDA announced a record $3.3B loan for the Oglethorpe Power facility in Monroe County, GA. The exact date is not given.

news.constructconnect.com
Research sources and reasoning (7 recorded sources)

medium confidence at research time

  1. opc.com/newgeneration/monroecounty/
  2. opc.com/plant-category/gas/
  3. electric.coop/oglethorpe-powers-new-natural-gas-plant-will-boost-reliability-local-economy
  4. news.constructconnect.com/usda-announces-3.3b-loan-for-oglethorpe-power-facility-in-georgia
  5. powermag.com/kiewit-chosen-as-epc-for-new-1425-mw-gas-fired-power-plant-in-georgia/
  6. enr.com/articles/62438-oglethorpe-power-picks-kiewit-unit-as-epc-for-25b-gas-fired-georgia-power-plant
  7. facebook.com/groups/1155605586732309/posts/1165575805735287/

Commercial operation date: None of the search snippets give a dated in-service target. The Power Engineering snippet mentioning a target operation date is truncated, so the LBNL proposed COD of 2028-03-31 is the only usable date. The plant is under construction, so this date is plausible but unverified.

Developer: The LBNL developer field is blank, so there is no shell LLC to compare. The Oglethorpe Power project page (opc.com), POWER Magazine, ENR and the USDA loan coverage all name Oglethorpe Power as owner and developer of the Smarr CC.

Status: Oglethorpe's project page lists Smarr CC as 'Under Construction'. America's Electric Cooperatives reports a groundbreaking on the $3.3B plant, so the LBNL queue state understates the project's progress.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Smarr CC project is a proposed 2000 MW gas-fired generation project located in Monroe County, Georgia. The project is being developed within the Georgia Transmission Corporation (GTC) service area. It is listed in the GTC interconnection queue as project GTC-GI-193, with an interconnection queue entry date of August 5, 2024.

The proposed commercial operation date for the Smarr CC project is March 31, 2028. The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is planned for the Big Smarr 500 kV substation.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

GA

County

Monroe

Grid Region

Southeast

Market

—

Developer

—

Utility

Georgia Transmission

Entity

GTC

Service Type

—

Point of Interconnection

Big Smarr 500 kV substation (TBD)

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-05-31

View all articles