Beaver Creek Solar
183 MW hybrid in Baldwin, GA · In queue since September 2023 · Proposed COD April 2027
183 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Entered GTC interconnection queue at Facility Study stage
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of April 2027. No independent news or press releases found to validate or contradict this date.
Developer: LBNL snapshot contains no developer information, and live search returned no results identifying the project sponsor or operating company.
Status: LBNL reports 'active' status with Facility Study underway as of September 2023 queue entry. No contradicting information in public domain.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Beaver Creek Solar is a proposed 183 MW hybrid solar and battery energy storage project in Baldwin County, Georgia. The project, which consists of 183 MW of solar generation, is located in the Southeast region and is being developed within the Georgia Transmission (GTC) service area.
The project is listed in the GTC interconnection queue as entry GTC-GI-184, with a queue entry date of September 20, 2023. Its proposed commercial operation date is April 1, 2027, and its interconnection status is currently in the System Impact Study phase. Beaver Creek Solar has been the subject of recent news coverage related to regulatory matters.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Baldwin
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Gordon - Milledgeville (White) 115 kV TL
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesBeaver Dam (AR)
Data-driven briefing on Beaver Creek Solar — fleet, generation, financial, and news signals.
Georgia Power at Wadley GA
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Beaver Creek Solar
Data-driven briefing on Beaver Creek Solar — fleet, generation, financial, and news signals.
Beaver
Data-driven briefing on Beaver — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.