Talbot Solar
150 MW generation in Talbot, GA · In queue since December 2021 · Proposed COD December 2023
150 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Facility Study
IA Phase
COD target: 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2 years
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-30
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Proposed commercial operation date per LBNL queue filing
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: LBNL queue lists proposed COD of 2023-12-30. No news or research findings available to confirm or contradict. Project marked operational in LBNL data, suggesting COD may have been met or is imminent.
Developer: LBNL queue snapshot contains no developer information. No news articles or press releases found through live search to identify the project sponsor or operating company.
Status: LBNL queue status is 'active' with is_operational flag set to true, indicating project has reached commercial operation. Interconnection agreement still in Facility Study phase.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Talbot Solar project is a proposed 150 MW solar generation facility in Talbot County, Georgia. The project is listed in the Georgia Transmission (GTC) interconnection queue as entry GTC-GI-157, with a queue entry date of December 1, 2021. The proposed commercial operation date is December 30, 2023. Its interconnection status is currently in the Facility Study phase.
The Talbot Solar project has been the subject of recent news coverage, with eight articles appearing in the press. These articles primarily focus on grid-related topics, with additional coverage of industry and development aspects of the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Talbot
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Talbot County Energy – Butler Sub
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesGeorgia Power at Wadley GA
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Georgia Power at Swainsboro
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Georgia Power at Jakin GA PV
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.