Crossroads Solar
150 MW hybrid in Liberty, GA · In queue since June 2021 · Proposed COD May 2024
150 MW
Capacity
1
Components
Solar
5y 1m
In Queue
Facility Study
IA Phase
COD target: 2024
Total Duration
2y 11m
Schedule
26 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-30
Original proposed COD per LBNL queue filing
Crossroads Solar is a proposed 150 MW hybrid solar and battery energy storage project in Liberty County, Georgia. The project, developed by an unknown entity, consists of 150 MW of solar generation capacity. It is located in the service territory of Georgia Transmission Corporation (GTC) and interconnects to the Ludowici - Riceboro 115 kV TL point of interconnection.
The project is listed in the GTC interconnection queue as project GTC-GI-152, with an original queue entry date of June 23, 2021, and a proposed commercial operation date of May 30, 2024. Its interconnection status is currently in the Facility Study phase. The Crossroads Solar project has been the subject of recent news coverage, with 10 articles categorized as industry, regulatory, and grid related.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Liberty
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Ludowici - Riceboro 115 kV TL
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Crossroads SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.