Union City Storage I
200 MW storage in Fulton, GA · In queue since December 2019 · Proposed COD November 2022
200 MW
Capacity
1
Components
Battery
6y 11m
In Queue
Facility Study
IA Phase
COD target: 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 11m
Schedule
48 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-11-30
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
LBNL proposed commercial operation date
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2022-11-30. No independent news or research sources found to verify or update this date. Given the project is marked operational in LBNL data, this date may represent actual COD.
Developer: No developer information available in LBNL queue snapshot, and no news or research sources identified the project developer or owner.
Status: LBNL queue data indicates is_operational=true, suggesting the 200 MW battery storage facility achieved commercial operation, likely around the proposed 2022-11-30 date.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Union City Storage I project is a proposed 200 MW battery storage project located in Fulton County, Georgia. The project is being developed within the Georgia Transmission (GTC) service area. It is listed in the GTC interconnection queue as project GTC-GI-132, with an entry date of December 11, 2019, and a proposed commercial operation date of November 30, 2022. Its interconnection status is currently in the Facility Study phase.
The project consists of 200 MW of battery storage capacity. The Union City Storage I project is proposed to interconnect at the Union City substation. The project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Fulton
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Union City substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesGeorgia Power at Wadley GA
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Georgia Power at Swainsboro
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Georgia Power at Jakin GA PV
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.