SR Metter
80 MW generation in Candler, GA · In queue since October 2019 · Proposed COD November 2025
80 MW
Capacity
1
Components
Solar
6y 9m
In Queue
Construction
IA Phase
COD target: 2025
Total Duration
6y 1m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-30
The SR Metter project is a proposed 80 MW solar generation project located in Candler County, Georgia. The project is being developed within the Georgia Transmission (GTC) interconnection queue as project GTC-GI-128. The queue entry date is October 10, 2019, with a proposed commercial operation date of November 30, 2025. The project's interconnection agreement status is currently listed as "Construction".
The proposed project is linked to the existing SR Metter operating plant (EIA plant ID 68250). Recent news coverage indicates the project has been featured in at least six news articles related to grid infrastructure.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Candler
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Statesboro - Vidalia 230 kV TL
Data Source
LBNL
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about SR MetterForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.