Limestone Solar
150 MW hybrid in Macon, GA · In queue since May 2019 · Proposed COD December 2021
150 MW
Capacity
1
Components
Solar
7y 2m
In Queue
Facility Study
IA Phase
COD target: 2021
Total Duration
2y 7m
Schedule
55 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
LBNL proposed commercial operation date
The Limestone Solar project is a proposed 150 MW solar and battery hybrid development in Macon County, Georgia. Interconnection is requested through the Georgia Transmission Corporation (GTC) queue, identified as GTC-GI-118. The project entered the queue on May 30, 2019, and has a proposed commercial operation date of December 31, 2021.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the North Americus _x0013_ Perry 115 kV TL. The solar component has a capacity of 150 MW. The developer is not specified in the available data.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Macon
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
North Americus – Perry 115 kV TL
Data Source
LBNL
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Limestone SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.