FPL-543
74.5 MW generation in Hendry, FL · In queue since January 2023 · Proposed COD October 2031
74.5 MW
Capacity
1
Components
Solar
3y 6m
In Queue
System Impact Study
IA Phase
COD target: 2031
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-10-31
FPL-543 is a proposed solar generation project located in Hendry County, Florida, with a total capacity of 74.5 MW. The project, developed by Florida Power & Light (FPL), is interconnected to the Florida Power & Light system near LaBelle. It entered the interconnection queue on January 6, 2023, and has a proposed commercial operation date of April 30, 2032. The project's interconnection status is currently in the System Impact Study phase.
The development project consists of 74.5 MW of solar photovoltaic generation. It is listed in the interconnection queue of Florida Power & Light. Recent news coverage has discussed the project's potential impact on the region's energy infrastructure.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
FL
County
Hendry
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
NRIS
Point of Interconnection
Near LaBelle
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project FPL-543Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.