FPL-425A
75 MW hybrid in Jackson, FL · In queue since February 2022 · Proposed COD March 2029
75 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Phase
COD target: 2029
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-03-01
The proposed FPL-425A project is a 75 MW solar and battery hybrid development in Jackson County, Florida. The project, being developed by a third party, consists of 75 MW of solar generation. It is interconnected to the Florida Power & Light (FPL) system at the Holmes Creek-Highlands City 230kV point of interconnection.
The project is currently in the Florida Reliability Coordinating Council (FRCC) interconnection queue, with an entry date of February 7, 2022. Its proposed commercial operation date is March 1, 2029, and the project is currently in the Facility Study phase of the interconnection process.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
FL
County
Jackson
Grid Region
Southeast
Market
—
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Service Type
NRIS
Point of Interconnection
Holmes Creek-Highlands City 230kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project FPL-425AForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.