FPL-378H
74.5 MW generation in Walton, FL · In queue since February 2020 · Proposed COD July 2027
74.5 MW
Capacity
1
Components
Solar
6y 5m
In Queue
Facility Study
IA Phase
COD target: 2027
Total Duration
7y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-31
The proposed FPL-378H project is a 74.5 MW solar generation project located in Walton County, Florida. The project, being developed by Florida Power & Light (FPL), entered the queue on February 5, 2020, and has a proposed commercial operation date of July 31, 2027.
The project is currently in the Facility Study phase of its interconnection process with Florida Power & Light. The point of interconnection is the Shoal River - Pinckard (APC) 230kV line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
FL
County
Walton
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
NRIS
Point of Interconnection
Shoal River - Pinckard (APC) 230kV line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.