Mule Deer Run Gas III
1,263 MW generation in Anderson, TX · In queue since June 2026 · Proposed COD July 2032
1,263 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
COD target: 2032
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-07-01
Mule Deer Run Gas III is a proposed natural gas-fired, combined-cycle generation project located in Anderson County, Texas. The development project is being advanced by Anderson Energy Center, LLC and has a total planned capacity of 1,263 MW. It is designed to interconnect to the grid at the Pin Oak 345 kV substation (#3308).
The project is listed in the interconnection queue of the Electric Reliability Council of Texas (ERCOT) under queue ID ERCOT-31INR0022, with a queue entry date of June 4, 2026. Its status in the queue is active, and its proposed commercial operation date is July 1, 2032. The provided data does not indicate the status of an interconnection agreement for the project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Anderson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Anderson Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#3308 Pin Oak 345KV
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Mule Deer Run Gas IIIForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.