Hackberry Draw Solar
652.96 MW generation in Jones, TX · In queue since August 2026 · Proposed COD April 2030
652.96 MW
Capacity
0
Components
2 months
In Queue
—
IA Status
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-04-30
Hackberry Draw Solar is a proposed photovoltaic solar generation project in Jones County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Orsted Onshore Development North America, LLC is developing the project, which has a planned total capacity of 652.96 megawatts (MW). The project would connect to the grid via a tap on the 345 kV West Shackleford (68000) to Clear Crossing (60515) Circuit 2 transmission line.
The project appears in the ERCOT interconnection queue under the identifier ERCOT-30INR0146, with a queue entry date of August 3, 2026. Its interconnection request is listed as active, and its proposed commercial operation date is April 30, 2030. The available data do not report the status of an interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Orsted Onshore Development North America, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV (68000) West Shackleford - (60515) Clear Crossing Ckt 2
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LNCRK_ALL
- POI Substation
- West Shackleford Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Hackberry Draw SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.