1,272.8 MW generation in Jack, TX · In queue since July 2026 · Proposed COD June 2030
1,272.8 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-14
Thunder Bird 1 Gas is a proposed natural gas-fired combined-cycle generation project in Jack County, Texas, with a total planned capacity of 1,272.8 MW. The developer of record is BKV Power Ventures Jack, LLC 3. The project is designed to connect to the grid by tapping a double-circuit transmission line that runs from the Jacksbro_5 substation (1429) to Willowck_5 (1421), and from Jacksbro_5 (1429) to Hendrch_5 (1443).
The project is listed in the Electric Reliability Council of Texas (ERCOT) interconnection queue under queue ID ERCOT-30INR0110, with a recorded queue entry date of July 8, 2026. Its status in the queue is active. The proposed commercial operation date is June 14, 2030. The available data do not indicate the status of an interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jack
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BKV Power Ventures Jack, LLC 3
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Double circuit line between Jacksbro_5 (1429) to Willowck_5 (1421) and Jacksbro_5 (1429) to Hendrch_5 (1443)
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Thunder Bird 1 GasForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.