Indigo Quill Gas (ERCOT-30INR0080) — Project Summary

Queue ID
ERCOT-30INR0080
Capacity
370.08 MW
Technology
Gas
Status
active
Location
Glasscock, TX
Region
ERCOT
Developer
RWE Clean Energy Development, LLC
IA Status
—

Indigo Quill Gas

ERCOT-30INR0080BetaActiveGasCombustion (gas) TurbineERCOTLive · ERCOT

370.08 MW generation in Glasscock, TX · In queue since March 2026 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

370.08 MW

Capacity

0

Components

8 months

In Queue

—

IA Status

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

2y 9m

Pre-Study0%
Queue EntryMar 10, 2026

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-29

Queue history
30INR0080 · 7 monthly ERCOT reports, Mar 2026 – Sep 2026

Projected COD moved

0 times

Dec 2028 → Dec 2028

Net change

0 months

first report to latest

Capacity

370 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 10, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 29, 2028
From queue filing
Developer in saved assessment
RWE Clean Energy Development, LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue; no IA yet (ercotqueue.com: 'Currently No IA; build-chance 9%'). One aggregator (interxdata) lists it as 'operational', which conflicts with LBNL and is likely a data error for a project queued in March 2026.
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. ercotqueue.com/project/30INR0080
  2. interconnection.fyi/project/ercot-30inr0080
  3. cleanview.co/power-projects/planned/natural-gas-power-plants/texas/30INR0080/indigo-quill-gas
  4. ercotqueue.com/developer/rwe-renewables-development-llc
  5. interxdata.com/projects/indigo-quill-gas-ercot-gis-report-30inr0080/

Commercial operation date: Only the LBNL filing gives a specific date (2028-12-29). Cleanview's 'Expected online 2028' is consistent with it, but it likely derives from the same queue data and is not an independent developer signal. No press releases or news give a different target.

Developer: LBNL and ercotqueue.com both list RWE Clean Energy Development, LLC as the filer. ercotqueue.com aggregates it under the RWE group, and RWE Americas is the parent. However, no source ties this gas project to a specific operating-company announcement, so I keep the filing entity name.

Status: LBNL shows active, is_operational false and no IA. interconnection.fyi and ercotqueue.com agree. The interxdata 'operational' label is an outlier and implausible for a project with a 2026 queue date and 2028 proposed COD.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Indigo Quill Gas is a proposed natural gas-fired generation project located in Glasscock County, Texas. Developed by RWE Clean Energy Development, LLC, the project would use combustion (gas) turbine technology and has a total proposed capacity of 370.08 megawatts (MW). The project would connect to the grid at the Sand Bluff 345 kV substation (bus 59902).

The project is listed in the Electric Reliability Council of Texas (ERCOT) interconnection queue under queue ID ERCOT-30INR0080, which it entered on March 10, 2026. Its queue status is active, and its proposed commercial operation date is December 29, 2028. The available data does not indicate the status of an interconnection agreement.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Glasscock

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

RWE Clean Energy Development, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

59902 SAND_BLUFF 345KV

Data Source

Live · ERCOT

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.