Moon Hammer
1,300 MW generation in Wheeler, TX · In queue since January 2026 · Proposed COD November 2030
1,300 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
IA → COD
4y 11m
Total Duration
10 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 24–48 months
Proposed COD: 2030-11-30
Projected COD moved
0 times
Nov 2030 → Nov 2030
Net change
0 months
first report to latest
Capacity
1300 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/natural-gas-power-plants/texas/30INR0077/moon-hammer
- cleanview.co/power-projects/planned/natural-gas-power-plants/ercot
- ercotqueue.com/leaderboard
- askthegrid.com/views/ercot-interconnection-queue
- interconnection.fyi/projects/state/TX
- interchange.puc.texas.gov/Documents/35077_2344_1570328.PDF
Commercial operation date: LBNL lists a proposed COD of 2030-11-30. Cleanview and Ask the Grid show the same Nov 30, 2030 date, but they appear to mirror the ERCOT queue filing. No developer press release or financing-backed target was found to confirm or revise it.
Developer: LBNL and the PUC interconnection agreement name the project LLC 'Moon Hammer LLC'. Cleanview's ERCOT gas list gives the developer as 'Synergetic Partners'. That is a single aggregator source, not a press release, so the parent attribution is unverified.
Status: LBNL shows 'active', and ercotqueue.com and interconnection.fyi both show it still active in the queue. There is no evidence of withdrawal, construction start, or operation. The IA status is ambiguous, so I did not upgrade it to 'IA Executed'.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Moon Hammer is a proposed 1300 MW gas-fired generation project located in Wheeler County, Texas. The project, developed by Moon Hammer LLC, is in the ERCOT interconnection queue as entry ERCOT-30INR0077, with a queue entry date of January 13, 2026. The proposed commercial operation date is November 30, 2030. An Interconnection Agreement (IA) was executed on December 19, 2025. The point of interconnection (POI) is a tap on the 345 kV line between Tesla and Grey.
The Moon Hammer project has been the subject of recent news coverage, appearing in 49 news articles, primarily related to deals and grid infrastructure.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wheeler
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Moon Hammer LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV line between Tesla & Grey
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Moon Hammer
Data-driven briefing on Moon Hammer — fleet, generation, financial, and news signals.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.