Moon Hammer (ERCOT-30INR0077) — Project Summary

Queue ID
ERCOT-30INR0077
Capacity
1300 MW
Technology
Gas
Status
active
Location
Wheeler, TX
Region
ERCOT
Developer
Moon Hammer LLC
IA Status
—

Moon Hammer

ERCOT-30INR0077BetaActiveGasCombustion (gas) TurbineERCOTLive · ERCOT

1,300 MW generation in Wheeler, TX · In queue since January 2026 · Proposed COD November 2030

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

1,300 MW

Capacity

0

Components

10 months

In Queue

—

IA Status

Signed Dec 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

IA → COD

4y 11m

Total Duration

10 months

Construction0%
Queue EntryJan 13, 2026

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 19, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2030-11-30

Queue history
30INR0077 · 9 monthly ERCOT reports, Jan 2026 – Sep 2026

Projected COD moved

0 times

Nov 2030 → Nov 2030

Net change

0 months

first report to latest

Capacity

1300 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 13, 2026
Interconnection agreement signedDec 19, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Nov 30, 2030
From queue filing
Developer in saved assessment
Synergetic Partners
Filed as Moon Hammer LLC
Status at research time
Active
Active in the ERCOT queue (queued 2026-01-13). An interconnection agreement is on file (LBNL IA date 2025-12-19), and ercotqueue.com shows 'IA, FIS pending'. No construction or permitting news was found.
Financing
Not recorded
Research sources and reasoning (6 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/natural-gas-power-plants/texas/30INR0077/moon-hammer
  2. cleanview.co/power-projects/planned/natural-gas-power-plants/ercot
  3. ercotqueue.com/leaderboard
  4. askthegrid.com/views/ercot-interconnection-queue
  5. interconnection.fyi/projects/state/TX
  6. interchange.puc.texas.gov/Documents/35077_2344_1570328.PDF

Commercial operation date: LBNL lists a proposed COD of 2030-11-30. Cleanview and Ask the Grid show the same Nov 30, 2030 date, but they appear to mirror the ERCOT queue filing. No developer press release or financing-backed target was found to confirm or revise it.

Developer: LBNL and the PUC interconnection agreement name the project LLC 'Moon Hammer LLC'. Cleanview's ERCOT gas list gives the developer as 'Synergetic Partners'. That is a single aggregator source, not a press release, so the parent attribution is unverified.

Status: LBNL shows 'active', and ercotqueue.com and interconnection.fyi both show it still active in the queue. There is no evidence of withdrawal, construction start, or operation. The IA status is ambiguous, so I did not upgrade it to 'IA Executed'.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Moon Hammer is a proposed 1300 MW gas-fired generation project located in Wheeler County, Texas. The project, developed by Moon Hammer LLC, is in the ERCOT interconnection queue as entry ERCOT-30INR0077, with a queue entry date of January 13, 2026. The proposed commercial operation date is November 30, 2030. An Interconnection Agreement (IA) was executed on December 19, 2025. The point of interconnection (POI) is a tap on the 345 kV line between Tesla and Grey.

The Moon Hammer project has been the subject of recent news coverage, appearing in 49 news articles, primarily related to deals and grid infrastructure.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Wheeler

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Moon Hammer LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345 kV line between Tesla & Grey

Data Source

Live · ERCOT

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.