Caldwell County Energy Center
1,500 MW generation in Caldwell, TX · In queue since February 2025 · Proposed COD April 2030
1,500 MW
Capacity
1
Components
Gas
1y 9m
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-04-30
Projected COD moved
0 times
Apr 2030 → Apr 2030
Net change
0 months
first report to latest
Capacity
1500 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- ercotqueue.com/project/30INR0031
- cleanview.co/power-projects/planned/natural-gas-power-plants/texas/30INR0031/caldwell-county-energy-center
- dchub.cloud/grid/ercot
Commercial operation date: Only the LBNL/ERCOT queue date of 2030-04-30 is available. Cleanview and DC Hub repeat it ("Expected online 2030"), but they appear to be derived from the queue data, so they are not independent confirmation. The news-extracted 2026 COD describes LCRA's separate Timmerman peaker project and was not applied here.
Developer: No source names a parent or operating company for this 1,500 MW project. The LCRA attribution in the news facts comes from a 2024 KVUE article about the Timmerman peaker plant, a different, smaller project, so it was not applied. FieldProspects and ercotqueue list only the project LLC.
Status: LBNL status is active and the ERCOT queue aggregators still list the project as active. The 'operational' status in the news facts comes from an unrelated 2020 Duke Energy solar release and was disregarded.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Caldwell County Energy Center is a proposed 1500 MW gas-fired generation project located in Caldwell County, Texas. Developed by Caldwell County Energy Center, LLC, the project consists of gas combustion turbine technology. It is listed in the ERCOT interconnection queue as entry ERCOT-30INR0031, with a queue entry date of February 3, 2025, and a proposed commercial operation date of April 30, 2030. The point of interconnection is the #7051 Misty Substation at 345kV.
The Caldwell County Energy Center development has been the subject of recent news coverage, with 10 articles categorized as relating to industry and grid topics.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Caldwell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Caldwell County Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#7051 Misty Substation 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.