Big Canyon Wind (ERCOT-30INR0018) — Project Summary

Queue ID
ERCOT-30INR0018
Capacity
1500 MW
Technology
Wind
Status
active
Location
Pecos, TX
Region
ERCOT
Developer
Longfellow Wind, LLC
IA Status
Facility Study

Big Canyon Wind

ERCOT-30INR0018BetaActiveWindERCOTLBNL + Live

1,500 MW generation in Pecos, TX · In queue since January 2025 · Proposed COD July 2030

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

1,500 MW

Capacity

1

Components

Wind

1y 10m

In Queue

Facility Study

IA Phase

COD target: 2030

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 6m

Facilities Study50%
Queue EntryJan 13, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-07-01

Queue history
30INR0018 · 21 monthly ERCOT reports, Jan 2025 – Sep 2026

Projected COD moved

1 time

Jul 2031 → Jul 2030

Net change

-12 months

first report to latest

Capacity

1500 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 13, 2025
Interconnection agreement signedDec 24, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jul 1, 2030
From queue filing
Developer in saved assessment
NextEra Energy Resources (inferred NextEra Energy affiliate)
Filed as Longfellow Wind, LLC
Status at research time
IA Executed
Active in the ERCOT queue. LBNL shows Facility Study, but a Standard Generation Interconnection Agreement between Big Canyon Wind, LLC and Texas-New Mexico Power Company dated Dec 22, 2025 appears in PUC filings. The ercotqueue aggregator still shows 'IA, FIS pending'.
Financing
Not recorded

Milestones in this assessment

IA executedDec 22, 2025Latest in this assessment

ERCOT Standard Generation Interconnection Agreement between Big Canyon Wind, LLC and Texas-New Mexico Power Company, dated Dec 22, 2025.

interchange.puc.texas.gov
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. ercotqueue.com/project/30INR0018
  2. ercotqueue.com/developer/longfellow-wind-llc
  3. cleanview.co/power-projects/planned/wind-farms/texas/30INR0018/big-canyon-wind
  4. interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&ItemMatch=0&DocumentType=ALL&SortBy=FilingParty&SortOrder=Descending
  5. lonestartransmission.com/content/dam/lonestar/us/en/pdf/2024/LoneStarCompliancePlan.pdf
  6. interchange.puc.texas.gov/Documents/36890_121_1429819.PDF

Commercial operation date: Only the LBNL proposed COD of 2030-07-01 is available. Cleanview ('Expected online 2030') and a Facebook post (COD 'around July') match it but appear to be derived from the queue data, so they are not independent confirmation. A Facebook post saying 'construction scheduled...' is truncated and gives no usable date.

Developer: LBNL and ercotqueue list the developer as the project LLC, Longfellow Wind, LLC. The project's PUC filings are under Big Canyon Wind, LLC, which is named in NextEra Energy's Lone Star Transmission affiliate compliance plan. Other entities in the PUC filing list, such as King Mountain Energy Storage and Palo Duro Wind, also appear to be NextEra affiliates. The parent is inferred from these affiliate lists, not from a direct press release.

Status: The PUC Interchange filing indicates an interconnection agreement was entered in December 2025, which is later than the LBNL Facility Study status. The agreement text was not reviewed in full, so execution is inferred from the filing snippet, and the project remains active in the queue.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Big Canyon Wind project is a proposed 1500 MW wind generation facility in Pecos County, Texas. Developed by Longfellow Wind, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-30INR0018, with a queue entry date of January 13, 2025. An Interconnection Agreement (IA) was executed on December 24, 2025. The proposed commercial operation date is July 1, 2031.

The proposed project has been the subject of recent news coverage related to regulatory matters. The point of interconnection (POI) is the 38441 Bottlebrush 345kV line.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Pecos

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Longfellow Wind, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

38441 Bottlebrush 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.