Rugged Prairie Wind
294.14 MW generation in Fisher, TX · In queue since September 2026 · Proposed COD December 2029
294.14 MW
Capacity
0
Components
1 month
In Queue
—
IA Status
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
Rugged Prairie Wind is a proposed 294.14 MW wind generation project in Fisher County, Texas. The development project is being advanced by Rugged Prairie Wind, LLC and would use wind turbine technology to generate electricity within the Electric Reliability Council of Texas (ERCOT) region.
The project is listed in the ERCOT interconnection queue under queue ID ERCOT-29INR0399 and currently holds an active status. It entered the queue on September 30, 2026, and has a proposed commercial operation date of December 1, 2029. The proposed point of interconnection is a tap on the 345 kV line between BUS #11305 Dermott and BUS #60706 Kirchhef.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Fisher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rugged Prairie Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV BUS #11305 Dermott- BUS #60706 Kirchhef
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Rugged Prairie WindForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.