Aurelius 3 Natural Gas
1,275 MW generation in Deaf Smith, TX · In queue since June 2026 · Proposed COD June 2030
1,275 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-30
Aurelius 3 Natural Gas is a proposed natural gas-fired generation project located in Deaf Smith County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Developed by IP Roman III Gas, LLC, the project has a total proposed capacity of 1,275 MW and is planned to use internal combustion technology. It is registered in the ERCOT interconnection queue under the identifier ERCOT-29INR0361.
The project entered the ERCOT queue on June 29, 2026, and currently holds an active status. Its proposed point of interconnection is the Deaf Smith station 345 kV substation (bus 23908). The developer has targeted a commercial operation date of June 30, 2030. The available data does not indicate the status of an interconnection agreement for the project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Deaf Smith
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Roman III Gas, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
23908 Deaf Smith station 345 kV
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Deaf Smith #6 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Aurelius 3 Natural GasForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.