Enfinity White Oak BESS
200 MW hybrid in Borden, TX · In queue since February 2026 · Proposed COD September 2029
200 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-17
Projected COD moved
1 time
Dec 2029 → Sep 2029
Net change
-3 months
first report to latest
Capacity
208 → 200 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue
Proposed commercial operation date per LBNL queue filing
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of September 2029. No independent news or press releases found to validate or contradict this target date.
Developer: LBNL filing entity 'EG White Oak LLC' follows Enfinity Global's standard project-LLC naming convention (EG prefix). Enfinity Global is a renewable energy developer active in Texas BESS projects.
Status: LBNL shows active queue status. Queue entry date of February 2026 indicates this is a recently submitted interconnection request with no public development milestones yet announced.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Enfinity White Oak BESS is a proposed 207.96 MW hybrid energy project in Borden County, Texas. Developed by EG White Oak LLC, the project consists of battery energy storage and another unspecified technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0267, with a queue entry date of February 25, 2026, and a proposed commercial operation date of December 18, 2029.
The point of interconnection for the project is the tap from the 138kV Key (1307) to the 138kV Gail (1308) transmission line. The project has appeared in recent news coverage regarding energy storage development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Borden
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
EG White Oak LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Key (1307) to 138kV Gail (1308)
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.