Sugarberry Solar SLF
125 MW generation in Kinney, TX · In queue since February 2026 · Proposed COD December 2029
125 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-18
Sugarberry Solar is a proposed 127.3 MW solar generation project located in Kinney County, Texas. The project, developed by EG Sugarberry LLC, is listed in the ERCOT interconnection queue as entry ERCOT-29INR0251, with a queue entry date of February 13, 2026. The proposed commercial operation date is December 18, 2029.
The project utilizes photovoltaic solar technology. It is currently listed as active in the interconnection queue. The point of interconnection is the 78255 Pinto Creek 138 kV location.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Kinney
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
EG Sugarberry LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
78255 Pinto Creek 138 kV
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ZIER_SLR_ALL
- POI Substation
- Pinto Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Sugarberry Solar SLFForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.