Riviera Gas
941.8 MW generation in Bell, TX · In queue since November 2025 · Proposed COD June 2030
941.8 MW
Capacity
1
Components
Gas
8 months
In Queue
Facility Study
IA Phase
COD target: 2030
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-14
Entered ERCOT interconnection queue in Facility Study phase
Proposed commercial operation date per LBNL queue filing
The Riviera Gas project is a proposed 941.8 MW gas-fired combined-cycle generation project located in Bell County, Texas. Developed by BKV-BPP Power, the project is in the ERCOT interconnection queue as entry ERCOT-29INR0206, with a queue entry date of November 5, 2025, and a proposed commercial operation date of June 14, 2030. The point of interconnection is the 3413 KNOB CREEK SWITCH SUBSTATION 345kV.
The Riviera Gas project has been the subject of recent news coverage, with 11 articles related to the industry, development, deals, and grid.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BKV-BPP Power
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3413 KNOB CREEK SWITCH SUBSTATION 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.