Riviera Gas
941.8 MW generation in Bell, TX · In queue since November 2025 · Proposed COD June 2030
941.8 MW
Capacity
1
Components
Gas
1 year
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-14
Projected COD moved
1 time
Oct 2029 → Jun 2030
Net change
+8 months
first report to latest
Capacity
942 → 637 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/natural-gas-power-plants/texas/29INR0206/riviera-gas
- ercotqueue.com/project/29INR0206
Commercial operation date: LBNL lists a proposed COD of 2030-06-14. Cleanview says the plant is 'expected to come online in June 2030', but it is a queue aggregator and not an independent developer or press signal. No news or press-release COD exists for this project.
Developer: LBNL and ercotqueue.com both name BKV-BPP Power, but ercotqueue.com is a queue tracker and no press release or corporate announcement was found. The news-extracted developer (Florida Power & Light) refers to the FPL Riviera Beach / Port Everglades plant in Florida and was discarded as a false match.
Status: LBNL shows active with ia_status 'Facility Study' and no IA date. ercotqueue.com confirms 'Currently No IA'. No evidence of withdrawal or construction was found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Riviera Gas project is a proposed 941.8 MW gas-fired combined-cycle generation project located in Bell County, Texas. Developed by BKV-BPP Power, the project is in the ERCOT interconnection queue as entry ERCOT-29INR0206, with a queue entry date of November 5, 2025, and a proposed commercial operation date of June 14, 2030. The point of interconnection is the 3413 KNOB CREEK SWITCH SUBSTATION 345kV.
The Riviera Gas project has been the subject of recent news coverage, with 11 articles related to the industry, development, deals, and grid.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BKV-BPP Power
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3413 KNOB CREEK SWITCH SUBSTATION 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all 5 articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.