Brazos Bend Storage SLF
243 MW generation in Milam, TX · In queue since September 2025 · Proposed COD September 2029
243 MW
Capacity
1
Components
Battery
1y 2m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-17
Projected COD moved
1 time
Aug 2029 → Sep 2029
Net change
+1 months
first report to latest
Capacity
247 → 243 MW
changed in the reports
Latest stage
Cancelled
last listed Jul 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Jul 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Project entered ERCOT interconnection queue at Facility Study stage
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of September 2029. No independent news or press releases found to validate or contradict this target date.
Developer: LBNL lists 'Grenergy USA' as developer, which appears to be the operating entity rather than a project-specific LLC. No news coverage found to confirm or provide additional detail on ownership structure.
Status: LBNL status shows 'active' with IA status at Facility Study stage. Queue date of September 2025 indicates very recent entry with no public milestones yet announced.
About
Generated Apr 10, 2026 · Predates Jul 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Brazos Bend Storage SLF project is a proposed 243 MW hybrid battery storage project located in Milam County, Texas. Developed by Grenergy USA, the project consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0164, with a queue entry date of September 11, 2025, and a proposed commercial operation date of September 17, 2029.
The project's point of interconnection (POI) is on the 345 kV Line (3765) GRISTMILL_5 to (39950) TNTNP_ONE_3. The project has appeared in recent news coverage regarding energy storage development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jul 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Grenergy USA
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Line (3765) GRISTMILL_5 to (39950) TNTNP_ONE_3
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Brazos Bend Storage SLF
Data-driven briefing on Brazos Bend Storage SLF — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.