Selenite Springs Solar (ERCOT-29INR0147) — Project Summary

Queue ID
ERCOT-29INR0147
Capacity
300 MW
Technology
Solar
Status
active
Location
Pecos, TX
Region
ERCOT
Developer
Selenite Springs Solar, LLC
IA Status
Facility Study

Selenite Springs Solar

ERCOT-29INR0147BetaActiveSolarERCOTLBNL + Live

300 MW generation in Pecos, TX · In queue since April 2025 · Proposed COD August 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

300 MW

Capacity

1

Components

Solar

1y 7m

In Queue

Facility Study

IA Phase

Signed Dec 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

8 months

IA → COD

2y 8m

Total Duration

8 months

Construction50%
Queue EntryApr 21, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 24, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-08-30

Queue history
29INR0147 · 18 monthly ERCOT reports, Apr 2025 – Sep 2026

Projected COD moved

3 times

Dec 2029 → Aug 2028

Net change

-16 months

first report to latest

Capacity

300 → 253 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedApr 21, 2025
Interconnection agreement signedDec 24, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Dec 31, 2027
Differs from queue: Aug 30, 2028
Developer in saved assessment
NextEra Energy Resources
Filed as Selenite Springs Solar, LLC
Status at research time
Active
Active in ERCOT queue at Facility Study stage; NextEra and Graphic Packaging announced a 250 MW VPPA-backed project in April 2026 targeting COD by end of 2027; Pecos County hearing held Aug 2025.
Financing
Not recorded

Milestones in this assessment

COD target2027Latest in this assessment

NextEra and Graphic Packaging target commercial operations by end of 2027 for the 250 MW Selenite Springs Energy Center.

constructionreviewonline.com
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. constructionreviewonline.com/new-250-mw-selenite-springs-energy-center-announced-for-west-texas/
  2. bicmagazine.com/projects-expansions/renewable-sustainability-h2-esg/graphic-packaging-holding-solar-agreement-nextera-texas/
  3. ercotqueue.com/project/29INR0147
  4. cleanview.co/power-projects/planned/solar-farms/texas/29INR0147/selenite-springs-solar
  5. renewatlas.com/project/selenite-springs
  6. app.nrgmap.com/queues/ercot-29inr0147

Commercial operation date: Construction Review (Apr 29, 2026) reports NextEra/Graphic Packaging plan commercial operations 'by the end of 2027', versus LBNL proposed COD of 2028-08-30 (~8 months later). Cleanview and RenewAtlas also show 2027-2028 online dates, so the gap is under a year and falls in the minor bucket.

Developer: LBNL lists the project LLC (registered in Texas July 2025). The April 2026 announcement states NextEra Energy Resources will develop and operate the Selenite Springs facility under a VPPA with Graphic Packaging.

Status: LBNL status is active and the ERCOT queue trackers (NRG Map, ercotqueue.com) confirm it. The offtake announcement shows the project is progressing, but no construction start is reported.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Selenite Springs Solar is a proposed 300 MW solar generation project located in Pecos County, Texas. The project, developed by Selenite Springs Solar, LLC, is interconnected within the ERCOT region under queue ID ERCOT-29INR0147. The project entered the queue on April 21, 2025, and has a proposed commercial operation date of August 30, 2028.

The project has an Interconnection Agreement (IA) date of December 24, 2025. The point of interconnection (POI) is Tap 138kV 38355 Leon Creek Switching Station - 38308 Woodhouse Switching Station. The project is currently listed as active in the interconnection queue.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Pecos

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Selenite Springs Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 38355 Leon Creek Switching Station - 38308 Woodhouse Switching Station

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
LEONLCPCT1_2
POI Substation
Leon Creek Switchyard

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.