MilamStation Power Secured Gas Generation
846 MW generation in Milam, TX · In queue since March 2025 · Proposed COD September 2029
846 MW
Capacity
1
Components
Gas
1y 8m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-25
Projected COD moved
2 times
Jan 2029 → Sep 2029
Net change
+8 months
first report to latest
Capacity
846 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-29inr0120
- ercotqueue.com/project/29INR0120
- app.nrgmap.com/queues/ercot-29inr0120
- cleanview.co/power-projects/planned/natural-gas-power-plants/texas/29INR0120/milamstation-power-secured-gas-generation
Commercial operation date: Only the LBNL proposed COD of 2029-09-25 exists. Aggregator sites (interconnection.fyi, cleanview.co) repeat the same date or 'expected online 2029', and none is an independent developer-backed signal.
Developer: LBNL names Power Secured Holdings LLC. ERCOT-derived trackers (interconnection.fyi, ercotqueue.com) list the owner as LCC-TX8, LLC, which is probably the project shell entity, but no press release identifies an operating parent. Power Secured Holdings LLC is kept as the only named developer. PowerSecure (powersecure.com) is unrelated and was not matched to this project.
Status: LBNL status is active, and nrgmap.com confirms active status as of Sept 2026. ercotqueue.com shows no IA, consistent with early-stage development. The interxdata 'operational' label and the infrasure ISO-NE claim conflict with LBNL and look like aggregator errors.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The MilamStation Power Secured Gas Generation project is a proposed 846 MW gas-fired combined-cycle generation project located in Milam County, Texas. Developed by Power Secured Holdings LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-29INR0120. The project entered the interconnection queue on March 24, 2025, with a proposed commercial operation date of November 1, 2027.
The interconnection point of contact is the #3377 LITTLE POND SWITCH 345kV. The project is currently listed as active in the ERCOT interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Power Secured Holdings LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#3377 LITTLE POND CREEK 345kv
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.