MilamStation Power Secured Gas Generation (ERCOT-29INR0120) — Project Summary

Queue ID
ERCOT-29INR0120
Capacity
846 MW
Technology
Gas
Status
active
Location
Milam, TX
Region
ERCOT
Developer
Power Secured Holdings LLC
IA Status
Facility Study

MilamStation Power Secured Gas Generation

ERCOT-29INR0120BetaActiveGasERCOTLBNL + Live

846 MW generation in Milam, TX · In queue since March 2025 · Proposed COD September 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

846 MW

Capacity

1

Components

Gas

1y 8m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 6m

Facilities Study50%
Queue EntryMar 24, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-25

Queue history
29INR0120 · 10 monthly ERCOT reports, Dec 2025 – Sep 2026

Projected COD moved

2 times

Jan 2029 → Sep 2029

Net change

+8 months

first report to latest

Capacity

846 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 24, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Sep 25, 2029
From queue filing
Developer in saved assessment
Power Secured Holdings LLC
From queue filing
Status at research time
Active
Active in ERCOT queue at Facility Study stage; no IA executed (ercotqueue.com shows 'No IA', build-chance 8%); no construction or financing announced.
Financing
Not recorded
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/ercot-29inr0120
  2. ercotqueue.com/project/29INR0120
  3. app.nrgmap.com/queues/ercot-29inr0120
  4. cleanview.co/power-projects/planned/natural-gas-power-plants/texas/29INR0120/milamstation-power-secured-gas-generation

Commercial operation date: Only the LBNL proposed COD of 2029-09-25 exists. Aggregator sites (interconnection.fyi, cleanview.co) repeat the same date or 'expected online 2029', and none is an independent developer-backed signal.

Developer: LBNL names Power Secured Holdings LLC. ERCOT-derived trackers (interconnection.fyi, ercotqueue.com) list the owner as LCC-TX8, LLC, which is probably the project shell entity, but no press release identifies an operating parent. Power Secured Holdings LLC is kept as the only named developer. PowerSecure (powersecure.com) is unrelated and was not matched to this project.

Status: LBNL status is active, and nrgmap.com confirms active status as of Sept 2026. ercotqueue.com shows no IA, consistent with early-stage development. The interxdata 'operational' label and the infrasure ISO-NE claim conflict with LBNL and look like aggregator errors.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The MilamStation Power Secured Gas Generation project is a proposed 846 MW gas-fired combined-cycle generation project located in Milam County, Texas. Developed by Power Secured Holdings LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-29INR0120. The project entered the interconnection queue on March 24, 2025, with a proposed commercial operation date of November 1, 2027.

The interconnection point of contact is the #3377 LITTLE POND SWITCH 345kV. The project is currently listed as active in the ERCOT interconnection queue.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Milam

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Power Secured Holdings LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

#3377 LITTLE POND CREEK 345kv

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.