Simsboro Storage
301.6 MW storage in Freestone, TX · In queue since June 2025 · Proposed COD March 2029
301.6 MW
Capacity
1
Components
Battery
1y 5m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-31
Projected COD moved
0 times
Mar 2029 → Mar 2029
Net change
0 months
first report to latest
Capacity
302 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- cleanview.co/power-projects/developers/matrix-renewables
- ercotqueue.com/project/29INR0119
- interconnection.fyi/project/ercot-29inr0119
Commercial operation date: Only the LBNL/ERCOT filing gives a COD (proposed 2029-03-31). Aggregator sites such as interconnection.fyi and ercotqueue.com repeat the same date, and no developer press release or news article gives a financing-backed target.
Developer: Cleanview lists Simsboro Storage (302 MW, Texas) in Matrix Renewables' development pipeline, which implies the LBNL filing LLC is a project shell. This rests on a single aggregator snippet with no corroborating press release.
Status: LBNL, interconnection.fyi and ercotqueue.com all show the project as active. One aggregator (interxdata) says 'operational', which contradicts the other sources and the LBNL is_operational=false flag, so I treated it as a data error.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Simsboro Storage project is a proposed 301.6 MW hybrid development located in Freestone County, Texas. The project, developed by Simsboro Storage LLC, consists of battery energy storage and another unspecified technology. It is listed in the ERCOT interconnection queue as entry ERCOT-29INR0119, with a queue entry date of June 11, 2025, and a proposed commercial operation date of March 31, 2029.
The project's point of interconnection (POI) is Tap Outlaw (3386) – Limestone (46020). The project is currently listed as active in the interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Freestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Simsboro Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Outlaw (3386) – Limestone (46020)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Simsboro Storage
Data-driven briefing on Simsboro Storage — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.