Cricket Storage
232.18 MW storage in Henderson, TX · In queue since April 2025 · Proposed COD October 2028
232.18 MW
Capacity
1
Components
Battery
1y 7m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-05
Projected COD moved
1 time
Jan 2029 → Oct 2028
Net change
-3 months
first report to latest
Capacity
234 → 232 MW
changed in the reports
Latest stage
Cancelled
last listed Mar 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue and began Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of October 2028. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing identifies Cricket Storage, LLC as developer. No news coverage or corporate announcements found to identify a parent operating company or confirm this is a project-specific LLC.
Status: LBNL shows active status in Facility Study phase as of April 2025 queue date. No news coverage found to indicate project progression beyond interconnection studies.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Cricket Storage is a proposed hybrid energy project located in Henderson County, Texas, with a total capacity of 232.18 MW. The project, developed by Cricket Storage, LLC, consists of battery energy storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0088, with a queue entry date of April 4, 2025.
The proposed commercial operation date for Cricket Storage is October 5, 2028. The point of interconnection is Tap 138kV #3179 Pauline - #3177 Eustace. The project has been mentioned in recent industry news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Mar 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Henderson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cricket Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV #3179 Pauline - #3177 Eustace
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Cricket Storage
Data-driven briefing on Cricket Storage — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.