Palomino Storage
152.5 MW generation in Hopkins, TX · In queue since November 2024 · Proposed COD May 2029
152.5 MW
Capacity
1
Components
Battery
2 years
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-01
Projected COD moved
2 times
Jun 2029 → May 2029
Net change
-1 months
first report to latest
Capacity
153 → 155 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue at Facility Study stage
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2028-12-31. No independent news or press releases found to validate or contradict this target date.
Developer: LBNL lists 'Palomino Renewables' as developer. No search results found to identify whether this is a shell LLC or operating company, or to reveal a parent entity.
Status: LBNL shows 'active' status in Facility Study phase. No news coverage found to indicate construction activity, financing, or status changes.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Palomino Storage (queue ID ERCOT-29INR0057) is a proposed energy development project in Hopkins County, Texas, developed by Palomino Renewables. The project is classified in the interconnection queue as a Solar+Battery generation project with a total capacity of 152.5 MW. However, its only itemized component is a 152.5 MW battery energy storage system, and no separate solar capacity is specified. The project would connect to the grid at a tap on the 345 kV line between the Monticello (1695) and Sulphur Springs (1697) substations.
The project sits in the interconnection queue of the Electric Reliability Council of Texas (ERCOT), which it entered on November 19, 2024. It currently holds an active status, and its interconnection agreement process is at the Facility Study stage. The proposed commercial operation date is May 1, 2029.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hopkins
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Palomino Renewables
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1695 Monticello - 1697 Sulphur Springs
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Monticello substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.