Amphion Solar Phase 1 (ERCOT-29INR0050) — Project Summary

Queue ID
ERCOT-29INR0050
Capacity
180.6 MW
Technology
Solar
Status
active
Location
Atascosa, TX
Region
ERCOT
Developer
Amphion Solar, LLC
IA Status
Facility Study

Amphion Solar Phase 1

ERCOT-29INR0050BetaActiveSolarERCOTLBNL + Live

180.6 MW generation in Atascosa, TX · In queue since October 2024 · Proposed COD September 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

180.6 MW

Capacity

1

Components

Solar

1y 7m

In Queue

Facility Study

IA Phase

COD target: 2028

Interconnection

Total Duration

3y 11m

Facilities Study50%
Queue EntryOct 10, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

About

The Amphion Solar project is a proposed 507.57 MW solar generation facility located in Atascosa County, Texas. Developed by Blue Heron Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0050, with a queue entry date of October 10, 2024. The proposed commercial operation date is September 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.

The point of interconnection is the TAP 345KV (#5709) FLOWERTON - (#5901) SAN MIGUEL LINE Ckt FOWRTN_SMIGL2. The Amphion Solar project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Atascosa

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Amphion Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

TAP 345KV (#5709) Fowlerton - (#5901) SAN MIGUEL LINE Ckt FOWRTN_SMIGL2

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.