Homestead Power (TEF-Due Diligence) (ERCOT-29INR0041) — Project Summary

Queue ID
ERCOT-29INR0041
Capacity
260.3 MW
Technology
Gas
Status
active
Location
Austin, TX
Region
ERCOT
Developer
Homestead Power LLC
IA Status
Facility Study

Homestead Power (TEF-Due Diligence)

ERCOT-29INR0041BetaActiveGasERCOTLBNL + Live

260.3 MW generation in Austin, TX · In queue since July 2024 · Proposed COD December 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

260.3 MW

Capacity

1

Components

Gas

2y 4m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 5m

Facilities Study50%
Queue EntryJul 30, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-15

Queue history
29INR0041 · 27 monthly ERCOT reports, Jul 2024 – Sep 2026

Projected COD moved

0 times

Dec 2029 → Dec 2029

Net change

0 months

first report to latest

Capacity

260 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJul 30, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 15, 2029
From queue filing
Developer in saved assessment
Homestead Power LLC
From queue filing
Status at research time
Active
Active — Facility Study phase as of July 2024 queue entry, no public construction or financing announcements
Financing
Not recorded

Milestones in this assessment

IA executedJul 30, 2024Latest in this assessment

Entered ERCOT interconnection queue, Facility Study phase

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of December 2029. No independent news or research sources found to validate or contradict this target date.

Developer: LBNL lists 'Homestead Power LLC' as developer. No news coverage or corporate information found to determine if this is a shell entity or identify any parent company.

Status: LBNL status shows 'active' with Facility Study underway. No news coverage found to indicate project progression beyond interconnection study phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Homestead Power is a proposed 260.3 MW gas-fired generation project located in Austin County, Texas. The project, developed by Homestead Power LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0041, with a queue entry date of July 30, 2024. The proposed commercial operation date is December 15, 2029.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 138 kV New Bremen #7271. The project has appeared in recent news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Austin

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Homestead Power LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

138 kV New Bremen #7271

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.