Commodus 2 Solar
502.1 MW generation in Swisher, TX · In queue since March 2025 · Proposed COD July 2029
502.1 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-30
Projected COD moved
1 time
Mar 2029 → Jul 2029
Net change
+4 months
first report to latest
Capacity
502 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-29inr0032
- ercotqueue.com/project/29INR0032
- substationscout.com/ercot/project/29inr0032-commodus-2-solar/
- cleanview.co/power-projects/planned/solar-farms/texas/29INR0032/commodus-2-solar
- groundtrace.io/developers/ip-blackwell-ii-llc-zqvguds6zp6li
- interxdata.com/projects/commodus-2-solar-ercot-gis-report-29inr0032/
Commercial operation date: Only the LBNL/ERCOT queue date (2029-07-30) exists. Aggregators such as interconnection.fyi ("proposed completion date is July 30, 2029") and cleanview ("Expected online 2029") repeat the queue data rather than adding independent developer guidance. No press release or news gives a financing-backed target.
Developer: Every source names IP Blackwell II, LLC, and none identifies a parent or operating company. The "IP" prefix may point to Intersect Power, but no source confirms this, so it is not asserted.
Status: LBNL lists the project as active with a Facility Study IA status, and ercotqueue.com, substationscout and Groundtrace agree it is queued with no IA and not under construction. interXdata's "operational" label conflicts with all of these and looks like a normalization error.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Commodus 2 Solar project is a proposed 502.1 MW solar generation facility in Swisher County, Texas. The project, developed by IP Blackwell II, LLC, is located within the ERCOT region and consists of photovoltaic solar technology. It is listed in the ERCOT interconnection queue as entry ERCOT-29INR0032, with a queue entry date of March 3, 2025, and a proposed commercial operation date of July 30, 2029.
The point of interconnection for the project is planned at the 345 kV double-circuit line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900). The project's interconnection status is currently active within the ERCOT queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Swisher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Blackwell II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.