Skyrider Wind (ERCOT-29INR0025) — Project Summary

Queue ID
ERCOT-29INR0025
Capacity
370 MW
Technology
Wind
Status
active
Location
Pecos, TX
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings, LLC
IA Status
Facility Study

Skyrider Wind

ERCOT-29INR0025BetaActiveWindERCOTLBNL + Live

370 MW generation in Pecos, TX · In queue since November 2024 · Proposed COD July 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

370 MW

Capacity

1

Components

Wind

2 years

In Queue

Facility Study

IA Phase

Signed Dec 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 1m

IA → COD

2y 7m

Total Duration

1y 1m

Construction50%
Queue EntryNov 19, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 23, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2028-07-01

Queue history
29INR0025 · 23 monthly ERCOT reports, Nov 2024 – Sep 2026

Projected COD moved

0 times

Jul 2028 → Jul 2028

Net change

0 months

first report to latest

Capacity

365 → 370 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 19, 2024
Interconnection agreement signedDec 23, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jul 1, 2028
From queue filing
Developer in saved assessment
NextEra Energy
Filed as NextEra Energy Interconnection Holdings, LLC
Status at research time
Active
Active in the ERCOT queue. An ERCOT standard generation interconnection agreement with TNMP was dated 2025-12-22 and filed at the Texas PUC. No evidence of construction start.
Financing
Not recorded

Milestones in this assessment

IA executedDec 22, 2025Latest in this assessment

ERCOT Standard Generation Interconnection Agreement between Skyrider Wind, LLC and Texas-New Mexico Power Company, filed at the Texas PUC (dated Dec 22, 2025).

interchange.puc.texas.gov
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=2340
  2. app.nrgmap.com/queues/ercot-29inr0025
  3. ercotqueue.com/project/29INR0025
  4. texas-biz.com/co/skyrider-wind-llc
  5. cleanview.co/power-projects/planned/wind-farms/texas/29INR0025/skyrider-wind

Commercial operation date: Only the LBNL/ERCOT queue date of 2028-07-01 exists. The NRG Map and Cleanview pages repeat it ('Expected online 2028') and are not independent developer or press confirmations. No developer announcement or financing-backed target was found.

Developer: The queue lists NextEra Energy Interconnection Holdings, LLC, but the project-level entity in the Texas PUC interconnection filing and the Texas foreign-LLC registration (Oct 2024) is Skyrider Wind, LLC. This looks like a NextEra project-LLC structure. No source explicitly names the parent, so the NextEra attribution is inferred from the entity name.

Status: NRG Map shows the queue status as active as of 2026-09-01, with the IA stage reached and the facility study started. One aggregator (interxdata) says 'operational', which conflicts with the queue data and with the 2028 COD, so I treated it as unreliable.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Skyrider Wind is a proposed 370 MW wind generation project located in Pecos County, Texas. The developer is NextEra Energy Interconnection Holdings, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0025, with a queue entry date of November 19, 2024. The proposed commercial operation date is July 1, 2028. The project's interconnection status is currently in the Facility Study phase.

The point of interconnection (POI) is the 138kV #38365 TNPINION. The project consists of 370 MW of wind generation capacity. The Skyrider Wind project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Pecos

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

NextEra Energy Interconnection Holdings, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

138kV #38365 TNPINION

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.