Skyrider Wind (ERCOT-29INR0025) — Project Summary

Queue ID
ERCOT-29INR0025
Capacity
370 MW
Technology
Wind
Status
active
Location
Pecos, TX
Region
ERCOT
Developer
NextEra Energy Interconnection Holdings, LLC
IA Status
Facility Study

Skyrider Wind

ERCOT-29INR0025BetaActiveWindERCOTLBNL + Live

370 MW generation in Pecos, TX · In queue since November 2024 · Proposed COD July 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

370 MW

Capacity

1

Components

Wind

1y 8m

In Queue

Facility Study

IA Phase

Signed Dec 2025

Interconnection

Queue → IA

1y 1m

IA → COD

2y 7m

Total Duration

1y 1m

Construction50%
Queue EntryNov 19, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 23, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2028-07-01

Cross-source intelligence
Beta
Low confidence·1 sources·as of 2026-06-01
Expected COD
2028-07-01
From queue filing
Developer
NextEra Energy Resources
Filed as NextEra Energy Interconnection Holdings, LLC
Status
Active
Active — early-stage development in Facility Study phase, IA execution targeted for December 2025
Financing
Unannounced
Key milestones
IA executedDec 23, 2025

Interconnection Agreement execution targeted for December 23, 2025

source
COD targetJul 1, 2028Most recent

Proposed commercial operation date of July 2028

source
About

Skyrider Wind is a proposed 370 MW wind generation project located in Pecos County, Texas. The developer is NextEra Energy Interconnection Holdings, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0025, with a queue entry date of November 19, 2024. The proposed commercial operation date is July 1, 2028. The project's interconnection status is currently in the Facility Study phase.

The point of interconnection (POI) is the 138kV #38365 TNPINION. The project consists of 370 MW of wind generation capacity. The Skyrider Wind project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Pecos

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

NextEra Energy Interconnection Holdings, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

138kV #38365 TNPINION

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.