Infinium Solar (ERCOT-29INR0019) — Project Summary

Queue ID
ERCOT-29INR0019
Capacity
401.6 MW
Technology
Solar
Status
active
Location
Howard, TX
Region
ERCOT
Developer
Jackalope Flats Solar, LLC
IA Status
Facility Study

Infinium Solar

ERCOT-29INR0019BetaActiveSolarERCOTLBNL + Live

401.6 MW generation in Howard, TX · In queue since August 2024 · Proposed COD July 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

401.6 MW

Capacity

1

Components

Solar

2y 3m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 11m

Facilities Study50%
Queue EntryAug 16, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-07-01

Queue history
29INR0019 · 26 monthly ERCOT reports, Aug 2024 – Sep 2026

Projected COD moved

0 times

Jul 2029 → Jul 2029

Net change

0 months

first report to latest

Capacity

402 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedAug 16, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jul 1, 2029
From queue filing
Developer in saved assessment
Jackalope Flats Solar, LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue. The system impact study is complete and the facility study has started, with no interconnection agreement yet (NRG Map, status as of 2026-09-01). Nothing indicates construction.
Financing
Not recorded
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. app.nrgmap.com/queues/ercot-29inr0019
  2. interconnection.fyi/project/ercot-29inr0019
  3. cleanview.co/power-projects/planned/solar-farms/texas/29INR0019/infinium-solar
  4. interxdata.com/projects/infinium-solar-ercot-gis-report-29inr0019/

Commercial operation date: Only queue-derived sources exist. LBNL, NRG Map (ERCOT data as of 2026-09-01) and Cleanview all show a proposed online date of 2029-07-01 (Cleanview says 'Expected online 2029'). No developer press release or news item gives a different date.

Developer: Only the LBNL/ERCOT filing entity (Jackalope Flats Solar, LLC) is named, and NRG Map repeats it. No parent or operating company could be identified. The Infinium e-fuels news (Project Roadrunner) concerns a different project and appears to be a name collision, so it was not used.

Status: LBNL and the ERCOT-derived NRG Map and interconnection.fyi pages agree the project is active. The interXdata 'operational' label conflicts with the ERCOT study phase (no IA) and was disregarded as a normalization error.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The proposed Infinium Solar project is a 401.6 MW solar generation facility located in Howard County, Texas. The project, under development by NextEra Energy Interconnection Holdings, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0019, with a queue entry date of August 16, 2024.

The project's proposed commercial operation date is July 1, 2029. Its interconnection status is currently in the Facility Study phase. The point of interconnection is #1058 Longshore_5 345kV. The Infinium Solar project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Howard

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Jackalope Flats Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

#1058 Longshore_5 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.