Aurelius 2 Wind
621.6 MW generation in Deaf Smith, TX · In queue since December 2023 · Proposed COD September 2028
621.6 MW
Capacity
1
Components
Wind
2y 11m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
Projected COD moved
0 times
Sep 2028 → Sep 2028
Net change
0 months
first report to latest
Capacity
623 → 622 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- ercotqueue.com/project/29INR0010
- cleanview.co/power-projects/planned/wind-farms/texas/29INR0010/-aurelius-2-wind
- app.nrgmap.com/queues/ercot-29inr0010
- ercotqueue.com/developer/ip-roman-wind-ii-llc
Commercial operation date: Only the LBNL/ERCOT filing gives a specific date (proposed COD 2028-09-30). Cleanview's 'Expected online 2028' appears to be derived from the queue data and is not an independent developer signal. The June 2028 COD and 'IA Executed' details on the infrasure page belong to the separate Aurelius Wind project (29INR0004) and were not used.
Developer: Only the queue filing entity is named, and ercotqueue.com lists it with 1 project. No press release or corporate source identifies a parent or operating company, so no parent is asserted.
Status: The LBNL status is 'active', and NRG Map shows it as active. ercotqueue.com reports 'No IA' with a 12% build-chance, which is consistent with an early-stage project.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Aurelius 2 Wind project is a proposed 623 MW wind generation facility in Deaf Smith County, Texas. Developed by IP Roman II, LLC, the project entered the ERCOT interconnection queue as ERCOT-29INR0010 on December 4, 2023. The proposed commercial operation date is September 30, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project will interconnect at the 23908 Deaf Smith station 345kV. The Aurelius 2 Wind project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Deaf Smith
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Roman Wind II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
23908 Deaf Smith station 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Deaf Smith #6 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.