Aurelius Wind
621.6 MW generation in Deaf Smith, TX · In queue since August 2023 · Proposed COD June 2028
621.6 MW
Capacity
1
Components
Wind
3y 3m
In Queue
IA Executed
IA Phase
Signed Oct 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 2m
IA → COD
2y 8m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–36 months
Proposed COD: 2028-06-30
Projected COD moved
2 times
Dec 2029 → Jun 2028
Net change
-18 months
first report to latest
Capacity
1168 → 622 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection agreement executed for the 621.6 MW Aurelius Wind project (POI: Deaf Smith 345 kV station).
app.nrgmap.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- app.nrgmap.com/queues/ercot-29inr0004
- interconnection.fyi/project/ercot-29inr0004
- ercotqueue.com/project/29INR0004
- ercotqueue.com/project/29INR0010
Commercial operation date: The only COD evidence is the ERCOT/LBNL proposed date of 2028-06-30. Aggregators (nrgmap, interconnection.fyi, cleanview) repeat the same date from the same ERCOT data, so they are not independent confirmation, and no developer press release or news item gives a different target.
Developer: Every source names IP Roman Wind, LLC. EIA-860 lists the owner of the matched facility as 'IP Roman, LLC'. No source names a parent or operating company, and the 'IP' prefix is not enough to attribute it to one. A sister project, Aurelius 2 Wind, is filed under IP Roman Wind II, LLC.
Status: LBNL shows IA Executed with status active. nrgmap, using ERCOT data as of 2026-09-01, confirms the active status, the completed studies and the IA date. The interxdata 'operational' label and the cleanview 'California' page conflict with this and look like aggregator errors, so I disregarded them.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Aurelius Wind project is a proposed 623 MW wind generation facility in Deaf Smith County, Texas. Developed by IP Roman, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0004, with a queue entry date of August 14, 2023. The proposed commercial operation date is June 30, 2028, and the project's interconnection status is currently in the Facility Study phase.
The project consists of 623 MW of wind generation capacity. It is slated to connect to the 23908 Deaf Smith station at 345 kV. The Aurelius Wind project has appeared in recent news coverage regarding renewable energy development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Deaf Smith
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Roman Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
23908 Deaf Smith station 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Deaf Smith #6 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.