Nabla Energy Storage II
750 MW storage in Parker, TX · In queue since November 2025 · Proposed COD September 2029
750 MW
Capacity
1
Components
Battery
1 year
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-17
Projected COD moved
1 time
Dec 2028 → Sep 2029
Net change
+9 months
first report to latest
Capacity
750 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-28inr0466
- ercotqueue.com/project/28INR0466
- cleanview.co/power-projects/planned/battery-storage-projects/texas/28INR0466/nabla-energy-storage-ii
- ercotqueue.com/developer/nabla-park-llc
Commercial operation date: No independent developer or press source exists; aggregators (interconnection.fyi, Cleanview) just mirror the queue filing, e.g. 'The proposed completion date is September 17, 2029.' These are not independent confirmation of a financing-backed target.
Developer: Only the LBNL filing entity and queue-tracker mirrors name Nabla Park LLC. No press release or corporate source identifies a parent or operating company behind this shell-style name.
Status: LBNL lists 'active', and ercotqueue.com shows 'No IA' with a low build-chance estimate, consistent with an early-stage queue position. One aggregator (interxdata) lists it as 'operational', which conflicts with the LBNL snapshot and the other sources and is likely a data error.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Nabla Energy Storage II project is a proposed 750 MW hybrid battery energy storage project located in Parker County, Texas. The developer is Nabla Park LLC. It is listed in the ERCOT interconnection queue as entry ERCOT-28INR0466, with a queue entry date of November 5, 2025, and a proposed commercial operation date of September 17, 2029.
The project is currently listed as active in the interconnection queue. The point of interconnection is on the 345 kV Line PARKER 5 1436 to BENBRK A T5 1869.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Parker
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Nabla Park LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tapping on the 345 kV Line PARKER_5 1436 to BENBRK_A_T5 ‚Äé1869
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.