Kilby1 Part 4 Large Block Simple Cycle (ERCOT-28INR0459) — Project Summary

Queue ID
ERCOT-28INR0459
Capacity
950 MW
Technology
Gas
Status
active
Location
Reeves, TX
Region
ERCOT
Developer
Energy Forge One LLC
IA Status
Facility Study

Kilby1 Part 4 Large Block Simple Cycle

ERCOT-28INR0459BetaActiveGasERCOTLBNL + Live

950 MW generation in Reeves, TX · In queue since November 2025 · Proposed COD April 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

950 MW

Capacity

1

Components

Gas

1 year

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

2y 5m

Facilities Study50%
Queue EntryNov 18, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-20

Queue history
28INR0459 · 11 monthly ERCOT reports, Nov 2025 – Sep 2026

Projected COD moved

0 times

Apr 2028 → Apr 2028

Net change

0 months

first report to latest

Capacity

950 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 18, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 20, 2028
From queue filing
Developer in saved assessment
Chevron U.S.A. Inc.
Filed as Energy Forge One LLC
Status at research time
Active
Active in ERCOT queue at Facility Study stage with no executed IA; aggregator build-chance score about 10%; no construction or permit announcements found.
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. ercotqueue.com/project/28INR0459
  2. ercotqueue.com/developer/energy-forge-one-llc
  3. gridfilings.com/
  4. quicksandcheck.com/texas/reeves-county/
  5. interconnection.fyi/project/ercot-28inr0459

Commercial operation date: Only the LBNL/ERCOT queue date (2028-04-20) exists, and aggregator sites (GridFilings 'Apr 2028', Quicksand Check 'Apr...') just repeat it. No developer press release or news gives an independent COD.

Developer: ercotqueue.com states 'Energy Forge One LLC is a filing entity of Chevron U.S.A. Inc', so the LLC is a project shell and Chevron is the parent. This comes from a single aggregator source, not a press release.

Status: LBNL and multiple aggregators (interconnection.fyi, GridFilings, infrasure) list the project as Active. ercotqueue.com shows 'No IA', and no evidence of construction or withdrawal exists.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Kilby1 Part 4 Large Block Simple Cycle project is a proposed 950 MW gas-fired generation project in Reeves County, Texas. Developed by Energy Forge One LLC, the project consists of gas combustion turbine technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0459, with a queue entry date of November 18, 2025, and a proposed commercial operation date of April 20, 2028.

The point of interconnection (POI) for the project is Tap 345KV 11098 SLKSW – 60404 SOLSTICE Ckt 1 & Ckt 2.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Reeves

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Energy Forge One LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345 11098 SLKSW – 60404 SOLSTICE Ckt 1 Tap 345 11098 SLKSW – 60404 SOLSTICE Ckt 2

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.