Brazos Energy Security
3,000 MW generation in Fisher, TX · In queue since October 2025 · Proposed COD September 2030
3,000 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-09-22
Brazos Energy Security is a proposed natural gas-fired generation project in Fisher County, Texas, developed by Golden Spread Electric. The development project would use combined-cycle gas technology and has a total proposed capacity of 3,000 MW. It is planned to interconnect at a tap on the 345 kV transmission line between the Tonkawa Switch (Bus #1048) and Dusty Road (Bus #11050).
The project is listed in the interconnection queue of the Electric Reliability Council of Texas (ERCOT) under queue ID ERCOT-28INR0456. It entered the queue on October 21, 2025, and its status is active. The proposed commercial operation date is September 22, 2030. The available data does not indicate the status of an interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Fisher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Golden Spread Electric
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV (Bus #1048) Tonkawa Switch – (Bus #11050) Dusty Road
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Brazos Energy SecurityForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.