Vista Bluff Wind II "Alternate POI"
290.4 MW generation in Upton, TX · In queue since September 2025 · Proposed COD December 2029
290.4 MW
Capacity
1
Components
Wind
1y 2m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
Projected COD moved
1 time
Dec 2028 → Dec 2029
Net change
+12 months
first report to latest
Capacity
290 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue for Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2029-12-31. No independent news or research sources found to validate or contradict this date.
Developer: Only LBNL filing entity available. No press releases or corporate announcements found to identify a parent company or operating entity distinct from the filing LLC.
Status: LBNL status shows Active with Facility Study in progress. No contradictory information found in research. Project appears to be in early interconnection study phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Vista Bluff Wind II "Alternate POI" project is a proposed wind generation facility with a total capacity of 290.4 MW. It is located in Upton County, Texas, and is being developed by Vista Bluff Windpower, LLC. The project is currently active in the ERCOT interconnection queue under queue ID ERCOT-28INR0447, with an entry date of September 22, 2025. The proposed commercial operation date is December 31, 2029.
The point of interconnection (POI) is the tap 345 kV (76000) North McCamey - (59903) Bearkat (Benedum 345 kV station that LCRA will build part of 24RPG024).
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Vista Bluff Windpower, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV (76000) North McCamey - (59903) Bearkat (Benedum 345 kV station that LCRA will build part of 24RPG024).
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Max 4 Wind
Data tables and metrics from the InfraSure database.
FPL Energy Oliver Wind II LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Wind queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
FPL Energy Oliver Wind I LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.