Maratua Solar
130.84 MW generation in Grimes, TX · In queue since October 2025 · Proposed COD December 2028
130.84 MW
Capacity
1
Components
Solar
1y 1m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
Projected COD moved
1 time
Dec 2028 → Dec 2029
Net change
+12 months
first report to latest
Capacity
131 → 101 MW
changed in the reports
Latest stage
Screening started
last listed Jun 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue in Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2029-12-31. No independent news or press releases found to validate or contradict this date.
Developer: Only LBNL filing entity 'BDPU Solar Maratua, LLC' is available. No news coverage found to identify parent company or operating entity behind this project-specific LLC.
Status: LBNL status shows 'active' in Facility Study phase with recent queue entry (Oct 2025). No news coverage to indicate construction progress or delays.
About
Generated Apr 10, 2026 · Predates Jun 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Maratua Solar project is a proposed 100.51 MW solar generation project located in Grimes County, Texas. Developed by BDPU Solar Maratua, LLC, the project consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0426, with a queue entry date of October 3, 2025, and a proposed commercial operation date of December 31, 2029. The point of interconnection is planned as a new 138kV connection on the 9 BEDIAS – 4 IOLA line.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jun 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Grimes
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BDPU Solar Maratua, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
New 138kV connection on 9 BEDIAS – 4 IOLA
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.