Yellow Leaf II BESS
205.74 MW hybrid in Kaufman, TX · In queue since July 2025 · Proposed COD September 2028
205.74 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-25
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The Yellow Leaf II BESS project is a proposed 205.74 MW hybrid battery energy storage project located in Kaufman County, Texas. The developer is Yellow Leaf 2 BESS LLC. It is listed in the ERCOT interconnection queue as entry ERCOT-28INR0412, with a queue entry date of July 22, 2025, and a proposed commercial operation date of September 25, 2028.
The project is listed as active in the interconnection queue. The point of interconnection is Tap 138kV 2727 CRANDALL1_8 - 2724 KAUFMN_8.
Generated from interconnection queue and public data sources
State
TX
County
Kaufman
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Yellow Leaf 2 BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 2727 CRANDALL1_8 - 2724 KAUFMN_8
Data Source
Live · ERCOT
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Yellow Leaf II BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.