Treehouse Solar (ERCOT-28INR0394) — Project Summary

Queue ID
ERCOT-28INR0394
Capacity
281.77 MW
Technology
Solar+Battery
Status
active
Location
Grimes, TX
Region
ERCOT
Developer
Treehouse Solar, LLC
IA Status
Facility Study

Treehouse Solar

ERCOT-28INR0394BetaActiveSolarBatteryERCOTLBNL + Live

281.77 MW hybrid in Grimes, TX · In queue since July 2025 · Proposed COD November 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

281.77 MW

Capacity

1

Components

Solar

1y 4m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 4m

Facilities Study50%
Queue EntryJul 29, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-13

Queue history
28INR0394 · 14 monthly ERCOT reports, Jul 2025 – Sep 2026

Projected COD moved

0 times

Nov 2028 → Nov 2028

Net change

0 months

first report to latest

Capacity

282 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJul 29, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Nov 13, 2028
From queue filing
Developer in saved assessment
Treehouse Solar, LLC
From queue filing
Status at research time
Active
Active — Facility Study phase in ERCOT queue, no public construction timeline announced
Financing
Not recorded

Milestones in this assessment

IA executedJul 29, 2025

Entered ERCOT interconnection queue

COD targetNov 13, 2028Latest in this assessment

Proposed commercial operation date per LBNL queue filing

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of November 2028. No independent news or press releases found to validate or contradict this target date.

Developer: Only LBNL filing entity 'Treehouse Solar, LLC' is available. No news coverage found to identify parent company or operating entity behind this project-specific LLC.

Status: LBNL shows 'active' status in Facility Study phase. No news coverage found to provide additional ground-truth on project advancement or delays.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Treehouse Solar, LLC is proposing a 281.77 MW solar photovoltaic generation project in Grimes County, Texas. The project, identified as ERCOT-28INR0394 in the ERCOT interconnection queue, entered the queue on July 29, 2025. The proposed commercial operation date is November 13, 2028.

The point of interconnection for the proposed project is the 345 kV Jewett (#3390) - Singleton (#44645) line. The project is currently listed as active in the ERCOT queue.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Grimes

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Treehouse Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap the 345 kV Jewett (#3390) - Singleton (#44645) line

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.