Mojo BESS
245.71 MW generation in Wilson, TX · In queue since April 2025 · Proposed COD June 2028
245.71 MW
Capacity
1
Components
Battery
1y 7m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
Projected COD moved
0 times
Jun 2028 → Jun 2028
Net change
0 months
first report to latest
Capacity
246 MW
unchanged in the reports
Latest stage
Cancelled
last listed Jan 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue at Facility Study stage
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of June 2028. No independent news or press releases found to validate or contradict this target date.
Developer: LBNL lists 'Power Synergy' as developer. No news coverage found to confirm whether this is an operating company or project LLC, and no evidence of parent company or ownership structure.
Status: LBNL status shows 'active' at Facility Study phase. No news or press releases found to indicate progression beyond interconnection studies.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Mojo BESS (queue ID ERCOT-28INR0350) is a proposed energy development project in Wilson County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Developed by Power Synergy, the project has a total proposed capacity of 245.71 MW. Although the queue lists its technology as Solar+Battery, its only reported component is a 245.71 MW battery energy storage system. No solar capacity is specified in the available data. The project is categorized as a generation project and plans to interconnect at a tap on the Elm Creek–San Miguel 345 kV transmission line (Circuits 1 and 2).
The project entered the ERCOT interconnection queue on April 25, 2025, and is listed as active. It is currently in the Facility Study stage of the interconnection process, which means an interconnection agreement has not yet been executed. Its proposed commercial operation date is June 30, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jan 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wilson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Power Synergy
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 5133 Elm Creek 5901 - San Miguel CKT 1 & 2
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Mojo BESS
Data-driven briefing on Mojo BESS — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.