Prairie Power Wind (ERCOT-28INR0307) — Project Summary

Queue ID
ERCOT-28INR0307
Capacity
302.9 MW
Technology
Wind
Status
active
Location
Mitchell, TX
Region
ERCOT
Developer
Prairie Power Wind, LLC
IA Status
Facility Study

Prairie Power Wind

ERCOT-28INR0307BetaActiveWindERCOTLBNL + Live

302.9 MW generation in Mitchell, TX · In queue since June 2025 · Proposed COD April 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

302.9 MW

Capacity

1

Components

Wind

1y 5m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 10m

Facilities Study50%
Queue EntryJun 5, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-04-17

Queue history
28INR0307 · 17 monthly ERCOT reports, May 2025 – Sep 2026

Projected COD moved

1 time

Oct 2028 → Apr 2029

Net change

+6 months

first report to latest

Capacity

292 → 303 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJun 5, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 17, 2029
From queue filing
Developer in saved assessment
Titus Low Carbon Ventures
Filed as Prairie Power Wind, LLC
Status at research time
Active
Active in the ERCOT queue, in the Facility Study phase with no IA executed. No construction or permitting news found; the project is described as planned or in progress.
Financing
Not recorded
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. tituslcv.com/portfolio
  2. cleanview.co/power-projects/planned/wind-farms/texas/28INR0307/prairie-power-wind
  3. interconnection.fyi/project/ercot-28inr0307
  4. quicksandcheck.com/texas/mitchell-county/

Commercial operation date: Only the LBNL/ERCOT proposed COD of 2029-04-17 exists. Cleanview ("Expected online 2029") and Quicksand Check ("Apr 2029, In study") appear to mirror the queue data rather than give an independent developer target, so they don't count as separate confirmation.

Developer: Titus Low Carbon Ventures' portfolio page lists "Prairie Power Wind. In Progress. Wind Capacity 300 MW", which matches the 302.9 MW LBNL filing under the project-named LLC. This is a name and capacity match only, with no press release or ownership document, so the link is likely but not firmly confirmed.

Status: LBNL lists the project as active in the Facility Study phase. Interconnection.fyi, Cleanview ("planned") and Quicksand Check ("In study") are consistent with this, and nothing indicates withdrawal or construction.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Prairie Power Wind is a proposed 302.9 MW wind generation project located in Mitchell County, Texas. The project, developed by Prairie Power Wind, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0307, with a queue entry date of June 5, 2025. The proposed commercial operation date is April 17, 2029.

The project has been the subject of recent news coverage, with 14 articles related to industry, regulatory, grid, and development aspects of the project.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Mitchell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Prairie Power Wind, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

TAP 345KV BUS #1058 LONGSHORE_5 - BUS #10053 CATTLEMEN_5

Data Source

LBNL + Live

ApplicantNational GridRTO Insider · 2025-03-10
AgencyFERCRTO Insider · 2025-03-10
RulingApprovalRTO Insider · 2025-03-10
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.