Jukebox Solar
281 MW generation in Frio, TX · In queue since June 2025 · Proposed COD July 2027
281 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
Projected COD moved
0 times
Jul 2027 → Jul 2027
Net change
0 months
first report to latest
Capacity
281 MW
unchanged in the reports
Latest stage
Cancelled
last listed Mar 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue, Facility Study phase
Proposed commercial operation date per ERCOT filing
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of July 2027. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing entity 'ACE DevCo NC, LLC' is available. No news coverage found to identify parent company or operating entity behind this project-level LLC.
Status: LBNL status shows 'active' with IA status at Facility Study stage. No news coverage found to provide additional ground-truth status updates.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Jukebox Solar is a proposed 281 MW solar photovoltaic generation project in Frio County, Texas. Developed by ACE DevCo NC, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0281, with a queue entry date of June 19, 2025. The proposed commercial operation date is July 1, 2027.
The project intends to interconnect at the 8221 BIG FOOT4A 138kV point of interconnection.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Mar 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Frio
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ACE DevCo NC, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8221 BIG FOOT4A 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.