Hittson Creek Solar
402.93 MW hybrid in Callahan, TX · In queue since December 2024 · Proposed COD December 2028
402.93 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4 years
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-15
Projected COD moved
0 times
Dec 2028 → Dec 2028
Net change
0 months
first report to latest
Capacity
404 → 403 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-28inr0245
- ercotqueue.com/project/28INR0245
- cleanview.co/power-projects/planned/solar-farms/texas/28INR0245/hittson-creek-solar
- infrasure.ai/project/ercot-28inr0246-hittson-creek-bess
- groundtrace.io/developers/174-power-global-properties-jvlgfdwrxqjaq
Commercial operation date: Only queue-derived data exists. cleanview says 'Expected online 2028' and interconnection.fyi says 'proposed completion date is December 15, 2028', but both mirror the ERCOT filing. No developer press release or news provides an independent COD.
Developer: LBNL, ercotqueue.com, groundtrace.io and interconnection.fyi all name 174 Power Global Properties, but these are queue-derived. No independent press release confirms the parent or operating company. The entity may be a Hanwha-affiliated developer, but the sources do not state this.
Status: LBNL and multiple queue trackers show active status with no IA. One aggregator (interxdata) says 'operational', which contradicts the Facility Study phase and the 2028 target, so it is likely a data error.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Hittson Creek Solar is a proposed 404 MW solar generation project located in Callahan County, Texas. The project, developed by 174 Power Global Properties, is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0245, with a queue entry date of December 19, 2024. The proposed commercial operation date is December 15, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection is planned for tapping the two 345 kV Lines: Sam Line Reactor (Bus# 68005) - Reata (Bus# 68051) and Latimer (Bus# 68008) - Reata (Bus# 68051). The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Callahan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
174 Power Global Properties
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tapping the two 345 kV Lines: Sam Line Reactor (Bus# 68005) - Reata (Bus# 68051) and Latimer (Bus# 68008) - Reata (Bus# 68051).
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.