Ciervo Wind
301.5 MW generation in Jim Hogg, TX · In queue since December 2024 · Proposed COD December 2028
301.5 MW
Capacity
1
Components
Wind
1y 11m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4 years
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
Projected COD moved
0 times
Dec 2028 → Dec 2028
Net change
0 months
first report to latest
Capacity
302 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- ercotqueue.com/project/28INR0242
- interconnection.fyi/project/ercot-28inr0242
- app.nrgmap.com/queues/ercot-28inr0242
- cleanview.co/power-projects/planned/wind-farms/texas/28INR0242/ciervo-wind
Commercial operation date: Only the LBNL proposed COD (2028-12-31) is available; Cleanview's snippet 'Expected online 2028' appears to be derived from the same queue data and is not an independent developer-backed target. No press release or news gives a different date.
Developer: The LBNL filing entity is RWE Clean Energy Development, LLC and ercotqueue.com lists the same developer. No source names a different operating company or an ownership change, and no project-specific press release confirms the developer.
Status: LBNL lists the project as active and the aggregator sites (interconnection.fyi, NRG Map, ercotqueue.com) agree. Nothing indicates withdrawal, an IA execution, or construction.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Ciervo Wind is a proposed 301.5 MW wind generation project located in Jim Hogg County, Texas. The development project is being pursued by RWE Clean Energy Development, LLC and consists of a single wind component totaling 301.5 MW. The project is planned to connect to the grid via a tap on the 345 kV DelSol7A–Cruce Circuit 2 transmission line (Tap 345 kV 80355 DelSol7A - 80079 Cruce CKT 2).
The project is listed in the Electric Reliability Council of Texas (ERCOT) interconnection queue under queue ID ERCOT-28INR0242, with a queue entry date of December 19, 2024. Its status in the queue is active, and it is currently in the Facility Study phase of the interconnection process. The proposed commercial operation date for Ciervo Wind is December 31, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jim Hogg
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RWE Clean Energy Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 80355 DelSol7A - 80079 Cruce CKT 2
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Max 4 Wind
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.