Dahlia Solar
200.98 MW generation in La Salle, TX · In queue since February 2025 · Proposed COD June 2029
200.98 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Facility Study
IA Phase
COD target: 2029
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-30
Entered ERCOT interconnection queue, Facility Study phase
Dahlia Solar is a proposed 200.98 MW solar generation project in La Salle County, Texas. Developed by Dahlia Energy LLC, the project consists of photovoltaic solar technology and is located within the Electric Reliability Council of Texas (ERCOT) region.
The project, identified as ERCOT-28INR0240 in the ERCOT interconnection queue, entered the queue on February 14, 2025, with a proposed commercial operation date of July 2, 2028. The point of interconnection is Tap 138kV 5723 Los Angeles - 5705 Fowlerton. The project's interconnection status is currently listed as active.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
La Salle
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dahlia Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 5723 Los Angeles - 5705 Fowlerton
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Los Angeles Heights Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Dahlia SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.