Neptune Gas Generation Plant
113.77 MW generation in Reeves, TX · In queue since December 2024 · Proposed COD March 2028
113.77 MW
Capacity
1
Components
Gas
1y 11m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-15
Projected COD moved
0 times
Mar 2028 → Mar 2028
Net change
0 months
first report to latest
Capacity
114 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue, Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of March 2028. No independent news or press releases found to validate or contradict this target date.
Developer: BPX Production Company is listed as developer in LBNL filing. BPX is a BP subsidiary operating in the Permian Basin. No evidence of shell LLC structure or ownership changes found.
Status: LBNL status shows Active with Facility Study phase. Recent queue entry (Dec 2024) indicates very early development stage with no construction or financing announcements yet.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Neptune Gas Generation Plant is a proposed natural gas-fired generation project located in Reeves County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Developed by BPX Production Company, the project has a total planned capacity of 113.77 MW, consisting entirely of gas-fired generation. The development project is identified in the ERCOT interconnection queue under queue ID ERCOT-28INR0219.
The project entered the ERCOT interconnection queue on December 19, 2024, and maintains an active status. It is currently in the Facility Study phase of the interconnection process and has not yet executed an interconnection agreement. The proposed point of interconnection is the 11200 Longpast_T8 138 kV facility. The project has a proposed commercial operation date of March 15, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BPX Production Company
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
11200 Longpast_T8 138kv
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.