Complex Serenity Wind
971 MW generation in Armstrong, TX · In queue since June 2025 · Proposed COD April 2029
971 MW
Capacity
1
Components
Wind
1y 5m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-16
Projected COD moved
1 time
Jul 2028 → Apr 2029
Net change
+9 months
first report to latest
Capacity
971 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-28inr0215
- ercotqueue.com/project/28INR0215
- app.nrgmap.com/queues/ercot-28inr0215
- cleanview.co/power-projects/planned/wind-farms/texas/28INR0215/complex-serenity-wind
- abc7amarillo.com/news/local/brazilian-company-serena-propels-texas-wind-energy-growth-with-billion-dollar-investment-in-armstrong-county-turbines-ercot-renewable-energy-antonio-bastos-steve-sherrill-claude-economic-development-corporation
Commercial operation date: Only the LBNL/ERCOT proposed COD of 2029-04-16 exists. Aggregator pages (interconnection.fyi: 'proposed completion date is April 16, 2029'; Cleanview: 'Expected online 2029') repeat the queue data and are not independent confirmation. No developer press release or news gives a financing-backed target.
Developer: Every usable source (ERCOT queue trackers, interconnection.fyi) names only Serenity Wind, LLC. A 2023-24 local news item describes Brazilian company SERENA investing in Armstrong County wind, but its snippet does not name this project or queue ID, so I did not treat SERENA as the parent.
Status: NRG Map, interconnection.fyi and ercotqueue.com all show the project as active with no IA, consistent with LBNL. The interXdata 'operational' label conflicts with LBNL's is_operational=false and the facility-study stage, so I treated it as a normalization error.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Complex Serenity Wind is a proposed 971 MW wind generation project located in Armstrong County, Texas. The developer is Serenity Wind, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0215, with a queue entry date of June 5, 2025. The proposed commercial operation date is April 16, 2029.
The point of interconnection (POI) for Complex Serenity Wind is a double tap 345 kV line between the Alibates (bus# 23900) to Tule Canyon (bus# 23914) and the Alibates (bus# 23900) to Midpoint Switch (bus# 23931) lines.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Armstrong
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Serenity Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Double tap 345 kV Alibates (bus# 23900) to Tule Canyon (bus# 23914) and the Alibates (bus# 23900) to Midpoint Switch (bus# 23931)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.